
Deep Tunnel Sewerage System, Phase 2
Tunnel lining, shaft and mined adit design, with geotechnical supervision.
Engineering contributions to Singapore’s transport, water and airport infrastructure.
These selected projects show the scope of SGT’s consultancy work. Project owners, contractors and SGT’s role are listed separately within each profile.

Tunnel lining, shaft and mined adit design, with geotechnical supervision.

Temporary works and design checking to support bored tunnel construction.

ERSS design and supervision for water treatment infrastructure.

Temporary works supporting TBM operations on the CRL–Punggol Extension.

TBM thrust frames, launch systems and temporary works for the Cross Island Line.

Tender design of segmental lining, adits and cross passages for the Cross Island Line.
SGT’s supplied track record, dated October 2026. Dates and roles below refer to that record; “present” means the reporting date.
2025–present
ERSS design consultancy for the ventilation building.
2024–present
Bored tunnel temporary works, TBM facilities, conveyor assessment and lifting foundations.
2024–present
Temporary works for TBM launching, operation and dismantling.
2024–present
Temporary works consultancy, including TBM thrust frame design.
2024–present
QP geotechnical supervision.
2023–present
Bored tunnel temporary works, TBM facilities and invert cast bridge.
2023–2024
QP tender design for tunnel lining, cross passages, TBM parameters and impact assessment.
2022–present
QP geotechnical supervision.
2022–2024
Temporary works consultancy and segment precast yard substation design.
2021–2026
Structural design of buried pipes, thrust blocks and fire hydrant pipe works.
2021
Segment lining joint checks and cross-passage construction support.
2020–2023
Temporary works, temporary-loading checks and BHS precast invert slab design.
2020–2025
ERSS design and supervision, and piling instrumentation and monitoring design.
2020–2021
Tender design of tunnel segmental lining, adits and cross passages.
2019
Design checking of bored tunnel segment lining joints.
2018–2024
QP geotechnical supervision; segmental lining, shafts and mined adit design.
2018–2019
Underpass pipe-roofing tunnel design for Entrances A and C.
2018–2019
Temporary entrance structure and shaft construction temporary works.
2018
ERSS design for water-holding facilities and enabling works.
2018
ERSS design for electrical works.
2018–2021
Geotechnical bearing-capacity assessment for PVD machine.
2018–2020
Temporary works design and construction support.
2018–2019
Temporary works design and construction support.
2018–2020
Temporary works design and construction support.
Speak with SGT about your project requirements.